Project Progress Reports

Zehntbauer Masonry Work

8/14/2002

The final brick sealing was successfully completed with the Frank Manor work at the end of July.

7/11/2002

The work is complete except for the sealing of the brick which will be done with the Frank Manor masonry work near the end of the month.

6/25/2002

The replacement work is half way complete and will finish up this week. Following, the masons begin to clean and reseal the entire south elevation of the building.

6/18/2002

The lobby and one office in the front of Zehntbauer have experienced leaks during heavy rains for some time now. After removing some of the brick from the upper south wall of the building, investigation shows a masonry system that has failed and allows water to run down the concrete inner wall and into the building. This project will remove three entire rows of brick, correct the flashing detail, and then clean and seal the entire wall. This work will last about three weeks.

Project Manager: Larry Atchison, x7844

Hartzfeld Roof Resaturation

6/5/2002

Gravel and flashing details were completed last week. The project is complete and we have a fully warrantied roof system in place.

5/29/2002

Roof saturation is complete. New gravel and flashing details are being completed this week and the project will be complete.

5/21/2002

Roofers are removing the existing gravel from the roofs of the buildings this week. This pea gravel is being stored by our Grounds Department for future drainage projects. When we get a stretch of forecasted good weather, the roofers will be back on the roofs to resaturate.

5/10/2002

The flat roofs of the four Hartzfeld buildings are in need of resaturation to extend warranties and keep the builidng dry for years to come. Next week, the roofing contractor will begin removing the existing gravel from the roofs. As dry weather permits, the roofs will be resaturated and new gravel installed.

Project Manager: Larry Atchison, x7844

Forest Exterior Painting

8/14/2002

After substantial completion was declared on the new residence halls on 7/31, our painters went back to Tamarack and finished the painting.

7/11/2002

All five resident buildings and handrails are complete. Half of Tamarack is done and we will wait to complete the north and east side in August, after substantial completion of the new residence halls.

6/25/2002

Juniper will be completed this week. Handrails continue to be worked on. Prep work has started on Tamarack.

6/18/2002

Spruce is about halfway completed. Summer conferences have moved into Spruce for the week. We have pulled off and continue to work on the many handrails throughout Forest. The upper floor painting of Tamarack has been started this week also.

6/12/2002

Alder has been completed and Manzanita will be completed this week as well. The crews will then shift to Spruce. All the handrails throughout the Forest complex are being sanded, prepped and painted as well.

6/5/2002

Pondersosa is complete and the crews are working on Alder this week. Alder will be completed next week before the first summer conference the following week.

5/29/2002

Foundations have been painted. Ponderosa should be completed this week and then we will move on to Alder which will have the same basic color scheme. Juniper, Spruce and Manzanita will follow with Tamarack completed last as the new residence halls wrap up.

5/21/2002

Pressure washing continues this week on Ponderosa, Spruce and Juniper. Painting will follow after all the buildings are washed. Some of the building foundations have already been painted. Parking will be blocked off around buildings at times to avoid overspray onto any vehicles.

5/10/2002

Facilities Services painters and student helpers will be painting the exteriors of all the Forest buildings this summer. Pressure washing begins on Monday, 5/13 and will continue all week. Painting will occur as weather permits. The colors were chosen to tie into the colors of the new Residence Halls that will be coming on line this fall.

Project Manager: Larry Atchison, x7844

Dubach Lounge Computer Labs

9/3/2002

Punch list items were completed last week and the labs are ready for the school year.

8/23/2002

The contractor has been completing punch list items this week and the labs will be ready for the start of school.

8/14/2002

There is a break in the schedule next week and we will use that time to complete the punch list items.

7/11/2002

The project is substantially complete. Our IT department was able to move the labs over, set up and be operational for the second session of summer school on time. Final punch lists are being assembled and the work will be completed in between classes and on weekends.

6/25/2002

Lighting delivery was delayed, but will be in this week for installation. Carpeting will be installed this week. Electricians are hoping to wrap up all their work by next week. The new tables have arrived and will be assembled and installed after lighting and carpet.

6/18/2002

Painting continues this week. Flooring and lighting are scheduled for this week. The furniture is arriving in town this week and arrangements are being made to have it delivered and installed as soon as flooring and lighting are complete.

6/12/2002

Electricians have pulled most of the wires and the low voltage contractor is terminating their connections this week. New lighting is on the way and will be installed next week. Flooring and painting will be done next week. The new furniture is scheduled to arrive next week as well.

6/5/2002

Electricians continue to run conduit for all the computers and media equipment. Drywall is being completed this week. Doors, mechanical ventilation and lighting to follow in the next two weeks.

5/29/2002

Demolition is complete. Electricians are busy running conduit through the dividing wall this week. Sound insulation and drywall will follow.

5/21/2002

Construction is under way. Abatement and wall framing were completed last week along with final planning for the IT Department. Concrete core drilling will occur, early in the mornings, the first three days this week. Electricians can then begin to bring conduit up through the floors and throughout Dubach for the two lab spaces.

5/10/2002

Construction begins Monday, 5/13, and will continue until July 1 when the project is turned over to the IT Department to complete the move of equipment. Wall framing, demo and rough-in electrical work all begin on Monday.

4/10/2002

Dubach Lounge in Templeton will be renovated this summer into new Mac and PC computer labs to replace the labs in Throckmorton. Throckmorton and the rest of the classroom buildings and the Faculty Office Building will be demolished in January of 2003 to make room for the new Social Sciences Building.

Dubach will have a wall built down the middle to divide it into seperate labs. Addtional ventilation will be added to the space along with new lighting. Carpet and paint will be included. The computers and teaching equipment will be brought over from Throckmorton.

Some electrical work will begin next week in the basement, but we will not disturb the function of the lounge until after school is complete. The construction will begin around May 15 and should be completed by July 1.

Project Manager: Larry Atchison, x7844

Coffee Cart Move and Bodine Renovation

1/7/2002

The move has started and will be complete by tomorrow. Facilities Services workers have keyed the doors and after the movers are done, will be in to secure bookcases and erect shelving.

12/11/01

Construction is complete. Carpet cleaning and locksmith work needs to be done this week. Preparations are being made for the move, scheduled for Jan 7 & 8.

11/27/01

Painting is nearly complete. Electrical finish work is being completed this week along with the networking. Ceiling tiles will be installed this week. Carpet and finish details will be wrapped up next week and the project should be complete by 12/7. Locks for the cabinets in the Staff Lounge will be installed this week for Staff and Bon Apetite.

11/20/01

The coffee cart is moved and operational. Cabinet locks will be installed next week to seperate Staff cabinet space and Bon Apetite space. The walls are framed, wired and are being drywalled this week. Painting, doors and finish work will begin next week.

11/14/01

The coffee cart is being moved out of the 2nd floor of Bodine and over to the 1st floor Staff Lounge of Watzek Library. The move will occur Friday, 11/16, and the cart should be operational again on Monday, the 19th. This is a temporary move until the Albany Renovation is completed which will provide a new food service area. The vacated space will be remodeled for three new offices and the space across the hall will also be renovated for more office space. The space is needed to move the remaining faculty and staff out of the 2nd floor of Albany so that construction can begin. The renovation work should be complete by 12/21/01 and allow the move to occur during Winter Break.

Project Manager: Larry Atchison, x7844

Campus Wide Heating Ventilation and Air Conditioning Maintenance

August 31, 2001

Boilers in all dorms, and Central Heating Plant have been refurbished and tuned up. Chillers at Central Heating Plant and Theater have been serviced for peak performance.

Bike Shop Move

1/7/2002

The move is complete and the Bike Shop will be operating in its new location after Winter Break.

12/18/01

Facilities crews will remove and then install the racks, pegboards, shelves, etc. on 12/20. A few items were moved in over the weekend and the balance will be moved on Thursday.

12/11/01

Painting is complete and the area is weather tight. Electricians have added lighting and outlets. The locks will be changed this week and the telephone installation is set up for this week also. Move in is scheduled for the weekend of 12/15 & 12/16.

11/16/01

Our crew has been working on getting the space weather tight and have run into weather delays. The exterior stairwell above has been tarped off to aid in drying out the concrete so that it may be properly sealed inside and out. We expect to complete this next week and then electricians and telecommunications can be run. This delays the move until December or over Winter Break.

11/2/01

The Bike Shop will be relocated out of Albany to allow for the renovation. The new location will be next to the Platteau in the Platt residence hall. We anticipate moving around Thanksgiving.

Project Manager: Larry Atchison, x7844

Boat Dock Shed

1/7/2002

Floatation blocks were installed last week under both docks. The results were excellent and the project is complete.

12/18/01

Floatation blocks have not yet been installed due to weather conditions. We will be installing additional floatation blocks under the sinking dock with the sailboats.

11/27/01

The contractor will be out December 5th, give or take one day, to install the additional floatation blocks under the dock.

11/13/01

NW Diving and Marine Services will be installing the 10-15 additional floatation blocks under the dock that the shed rests on. Currently scheduled for the last week of November.

10/8/01

Power, lighting and rough in for the phone are complete. Phone service to be brought on line this coming week. Additional floatation for the dock is being investigated.

9/13/01

The shed is built and being used. Locks were changed this week. Electrical power, lighting and telephones to be installed still, rescheduled for this week.

9/4/01

The shed has been erected and has the skin on the walls and the roof install. The doors will be installed this morning and keyed this afternoon. Power and phone lines will be connected this week as well.

8/27/01

The shed has been delivered this afternoon to the contractor here on the main campus. It will be transported down to the dock tomorrow for immediate assembly.

8/22/01

Manufacturer has delayed orginal ship date. The new arrival is scheduled for Monday, 8/27. The general contractor, Kem's Woodworks, will double up crews to get the building complete prior to school opening, 9/4.

Project Manager: Larry Atchison, x7844

Platt Stairs

1/14/2002

Complete. There is one small section on the landing that needs to be replaced and that should be done this week.

1/7/2002

Removal of the old treads were completed last week. Today the floor covering contractor is beginning to install the new treads. The work should be completed by Wednesday, 1/9.

12/18/01

The existing stair treads from the main wood floor entry down to the Platteau will be replaced over Winter Break. The existing treads will be removed the first week of January and the new treads will be installed on Monday and Tuesday, the 7th & 8th. The area will blocked off during the project.

Project Manager: Larry Atchison, x7844

Spruce Kitchen Remodel

1/29/02

The punch list work was completed last week, the project is complete.

1/23/2002

The work is basically complete and the kitchen is already being used. Secondary light switches will be added for the under cabinet lighting.

1/14/2002

Cabinets, flooring and painting are complete. The plumbing and electrical fixtures are being installed today and Tuesday. Appliances arrive Tuesday. The door will then be installed and punch list items will be completed this week.

1/7/2002

Demo has been completed. Rough-in plumbing and wiring is complete and drywall has been hung. Drywall finish and painting begins today. Cabinets and flooring are due at the end of this week. Next week will be electrical finish, plumbing finish, appliance and door installations and final clean-up.

12/18/01

Demo will actually begin on Wednesday, 12/26, by DPR Construction.

12/11/01

Finishes have been selected and materials are on order.

11/28/01

We are going to remodel one of the first floor kitchens over Winter Break. We will open up the existing divided space to create a better functioning galley style kitchen complete with new cabinets and appliances. Work will begin 12/21/01 and will be completed by 1/19/02.

Project Manager: Larry Atchison, x7844