School navigation

Information Technology

Counseling Clinic Upgrades

15-SI-00100

Timeline

´╗┐Project Stage: Implementation

Project Summary: Upgrade network bandwidth and improve systems in order to better support the computing environment at the Barbur Clinic

Project Lead: Trevor/Tim

Relevant changes following completion: Faster network for the Barbur Clinic 

Anticipated service disruptions: Some downtime as computers are upgraded, no large disruptions

Additional considerations:

Project Submitted: 12/1/2014

Project Initiation: 12/5/2014

Project Milestones:

  1. Find funding from grad school for increased network speed 
  2. Upgrade network speed
  3. Upgrade computers

Completed Project:

Anticipated Quarter of Completion: Quarter 1

Executive Council Priority Tier: Tier 1

Last Updated: 7/27/2015

Project Charter Page