Holmes Hall Construction Update

January 04, 2012

Well, it’s a little damp out here today…  The framers are continuing to roll trusses above the 5th level.  Since 10/12 pitched roof trusses are to be installed in 3 parts, the bottom level is almost complete and ready for mid-level on Friday.  The exterior sheeting was approved on specific elevations to allow for the WRB (weather resistant barrier / Tyvek) installation to begin.  The mechanical, plumbing and electrical (MEP) subcontractors are continuing their rough in from the 1st through the 3rd levels.  The drywall subcontractor is currently prerocking the corridor ceilings on the 4th level in preparation for the MEP subs.