lawexp_arcCurrent Schedule:

All major mechanical equipment is now in the building and the lower level of the building has been framed. The cloud ceilings on levels 1 and 2 have also been framed. The Boley demolition work has moved ahead through all the floor cut outs for new floor ducts and the focus is now on completion of the underground work in the next two weeks

Architect:
Soderstrom Architects PC

General Contractor:
Hoffman Contruction

Start Date: July 11, 2000

Substantial Completion: Winter, 2002

 

 