Electronic Door Locks

16-SI-0185

Timeline

Project Stage: Planning

Project Summary: The primary stated objective of the project is to install electronic locks, accessed by a swipe card and managed by our access control software, on the exterior of all campus buildings that don’t already have them.  A secondary objective is to group all exterior doors into a single access group so that in the case of an emergent security situation, Campus Safety could quickly lock down all of the buildings in short order.

Project Lead: Trevor Dodson

Relevant changes following completion:

Anticipated service disruptions: 

Additional considerations: 

Project Submitted: 10/9/2015

Project Initiation: 10/2015

Project Milestones:

  1. Card swipe access on exterior buildings in the academic and administrative areas of the campus. (Residential buildings are already so equipped.)

  2. Access grouping in Lenel Access Control Software to lock all exterior doors (including existing doors with card swipe access) quickly.

Completed Project: Indicated doors will have swipe access and be monitored by Lenel. Doors will support future emergency lockdown.

Anticipated Quarter of Completion: Quarter 1

Executive Council Priority Tier: Tier 1

 

Last Updated: 5/11/2016

Project Charter