July 18, 2018

Howard Bridge:

Due to existing site conditions, we have lost some momentum on the Howard bridge. In order to regain that momentum, we have revised the schedule and will continue to work on the north side of the bridge until sewer repairs on the south end are completed. The revised schedule will be available to the public soon.

Templeton Bridge:

The initial demolition of the bridge railing is complete. We are patiently waiting on the completed crane pick plan in order to schedule the removal of the remainder of the bridge. 